CONSTRUCTION (INSTALLATION)

Membrane Installation

STEP 1
Installing a safety net to the area where membrane fabric will be applied

STEP 2
Installing a temporary membrane support

STEP 3
Taking the membrane fabric prepared to the assembly area

STEP 4
Unloading the membrane fabric to the assembly area

STEP 5
Preparation of the assembly area

STEP 6
Opening on the assembly area

STEP 7
Pulling the membrane fabric to the assembly area

STEP 8
Pulling the membrane fabric to the assembly area (appearance from below)

STEP 9
Installing aluminum profiles around the membrane

STEP 10
Carrying out the membrane tensioning process

STEP 11
Carrying out the final tensioning processes

STEP 12
Tensioning the membrane fabric (final form)

STEP 13
The form with necessary pre-stressing made

STEP 14
Making the membrane insulations

STEP 15
Ready membrane with insulations completed